Wednesday, December 21, 2011

Work Moves Inside as Winter Sets In

Although some members of the construction crew had been re-pointing brick on the façade of the building, the majority of the work has been moving inside as the weather changes. The building uses large portable heaters to provide temporary heat in the building during construction.

During the week of December 12, the crew focused on preparing for future systems. They started work on the fan coil unit that will deliver the HVAC to each classroom and the HVAC ductwork was assembled on the middle floor. Pipes were installed on the third floor for new restrooms.

Core holes were drilled through the concrete floors to supply water, gas, drainage for the science room labs.