Sunday, April 8, 2012

Diverse Phases of Work Completion Represented Throughout the Site

On any given day, there are 40 to 50 members of the renovation construction crew working on the site of the middle school. The crew is working on projects that represent all phases of construction from an initial phase to what could be considered a finishing or completion phase.

The work on some of the upper level classrooms and restrooms is close to the final phases including the preparing the floors for the installation of vinyl composite tile, VCT; finalizing the installation of VCT in classrooms: or completing the installation of ceramic tile in restrooms and hallways.

Block work on the cafeteria addition and loading dock area moved the construction along at the one end of the building at the same time QV maintenance workers were on the site to learn about the new rooftop HVAC units including how to maintain the new systems.

While the brick was being installed on the gym extension, demolition and construction was being started in areas where the new auditorium is being built.

The new addition for the integrated arts addition started to take shape with block work for the new elevator shaft. The interior of the old auditorium was demolished including the old balcony area while installation was started on the gray beams for the new auditorium. 